Paver calculator

How many pavers to order once the joints and cuts are counted, and everything that goes underneath them: road base, bedding sand and jointing sand, in the tonnes and kilograms suppliers sell them in.

Quick answer

Pavers per m² = 1 ÷ ((length + joint) × (width + joint)), then add 5 % for cuts. A 400 × 400 mm paver is 6.25 per m² with no joint, or 6.16 with a 3 mm joint, so a 20 m² patio needs 20 × 6.16 × 1.05 = 130 pavers.

Underneath a patio goes about 75 mm of compacted road base (3.3 t for 20 m²) and 25–30 mm of washed bedding sand (0.9 t). Dig to the paver thickness plus those two layers: 40 + 30 + 75 = 145 mm. Driveways need thicker pavers and about 150 mm of base.

Your area

Shape
m
m

Your pavers

mm
mm

Base layers

mm
mm

Cuts: 2 % suits a large simple rectangle, 5 % a typical patio, 10 % herringbone or curves. Manufacturers ask for 50–150 mm of compacted road base under foot traffic depending on the soil, and 25–30 mm of washed sand to bed the pavers. Choosing "Driveway" sets the base to 150 mm.

Prices (optional)

$
$
$

Example prices only, before delivery: aggregates from a Sydney landscape supplier's September 2026 list, pavers a mid-range concrete paver. Enter your own quotes.

Result

You need

20.00 m²
Pavers
130
Road base
3.30
tonnes
Bedding sand
0.90
tonnes
Jointing sand
18
kg
ItemQuantityCost

Road base is priced by weight at its compacted density (2.2 t/m³), so the tonnes cover the finished layer; a loose load is about 10 % bigger by volume. Estimates only – check the laying guide for the pavers you buy.

How the calculator works it out

Most online paver calculators divide the area by the size of one paver and stop there. That ignores the joint. With 3 mm joints, a 200 × 100 mm paver takes up 203 × 103 mm of ground, and the count drops by about 4 %. The calculator also works out the three layers underneath, which is where most first-time pavers under-order.

pavers per m² = 1 ÷ ( ( L + joint ) × ( W + joint ) )  ·  pavers = ⌈ area × per m² × (1 + cuts) ⌉
road base (t) = area × base depth × 2.2  ·  bedding sand (t) = area × bed depth × 1.5
jointing sand (kg/m²) = ( 1/L + 1/W ) × joint × thickness × 1,500

The jointing sand line assumes every joint is filled to the full depth of the paver. It lines up with the coverage one New Zealand jointing sand maker publishes: 3.3 kg/m² for 200 × 100 × 50 mm pavers and 1.1 kg/m² for 400 × 400 × 50 mm.

How many pavers per square metre?

Manufacturers' tables use the nominal count, with no joint. Real joints of 2–3 mm, or 4–6 mm for large formats, lower the count a little. The difference is small per square metre but adds up over a driveway.

Paver (mm)Typical thicknessPer m², no jointPer m², 3 mm joint
600 × 60040–50 mm2.782.75
600 × 400 (bluestone)20–30 mm4.174.12
600 × 30020–50 mm5.565.47
500 × 50040–50 mm4.003.95
400 × 40040 mm6.256.16
300 × 30011.1110.89
230 × 115 (clay brick paver)50 mm37.836.4
200 × 20050 mm25.024.3
200 × 100 (Holland)50 or 80 mm50.047.8

Thickness depends on the traffic. Pavers up to 40 mm thick are for foot traffic only. The Concrete Masonry Association of Australia recommends 60 mm pavers for light vehicles and 80 mm laid in herringbone for heavier ones.

How deep should the base be?

Every Australian and New Zealand laying guide agrees on the order of the layers: compacted crushed rock, then a thin screeded bed of sand, then the pavers. They differ on the depth of the base, because it depends on the soil and the traffic.

SourcePatio or pathDrivewayBedding
Austral Masonry50 mm compacted road baseConcrete base recommended30 mm washed river sand
National Masonry100–150 mm road base, or 75 mm concreteEngineer's advice; compact in 50 mm layersAbout 30 mm coarse washed sand
Australian Paving Centre75 mm compacted150 mm compacted30 mm washed sand
Firth (NZ)50–75 mm GAP20/40100–150 mmAbout 20 mm
NZS 3116 (via Urban Paving, NZ)50 mm on average soil100 / 75 / 50 mm on weak / average / firm soil30 mm

The calculator starts at 75 mm for foot traffic and 150 mm for a driveway, which sits in the middle of those ranges. On soft or reactive clay, or where water lies after rain, go deeper. The paver laying guide walks through each layer step by step.

Worked example: a 5 × 4 m patio in 400 × 400 pavers

  1. Area 20 m². Pavers per m² with 3 mm joints: 1 ÷ (0.403 × 0.403) = 6.16.
  2. Pavers: 20 × 6.16 × 1.05 for cuts = 129.3, so order 130.
  3. Road base: 20 × 0.075 m × 2.2 t/m³ = 3.3 t. At a 500 kg legal payload that is 7 loads in a 6×4 trailer, so pay for delivery (see the trailer load calculator).
  4. Bedding sand: 20 × 0.03 × 1.5 = 0.9 t.
  5. Jointing sand: (2.5 + 2.5) × 0.003 × 0.04 × 1,500 = 0.9 kg/m², so 18 kg.
  6. Dig depth: 40 + 30 + 75 = 145 mm below the finished paving level, plus the fall.

Fall and clearance from the house

Paving next to a house has to shed water away from it. In Australia the National Construction Code asks for the ground around a slab to fall at least 50 mm over the first metre. Paved surfaces in low-rainfall areas may fall 25 mm. The slab must sit at least 50 mm above paving that slopes away, and the brick damp-proof course usually 75 mm above it. In New Zealand, BRANZ recommends a 1:25 fall away from the building. E2/AS1 asks for the floor to be 100 mm above paving for brick veneer and 150 mm for other claddings. Never pave over weep holes or vents. Check these clearances before you dig, because they set your finished level.

Paver questions

How many 400 × 400 pavers do I need per square metre?

6.25 with no joint, or 6.16 with a 3 mm joint. Add about 5 % for cuts: a 10 m² area needs 65 pavers.

How much road base do I need under pavers?

Area × compacted depth × 2.2 t/m³. A 75 mm base under a patio is 0.165 t per m², so 1.65 t for 10 m². A 150 mm driveway base is 0.33 t per m².

Should I bed pavers on sand or crusher dust?

Most Australian paver makers specify washed river sand, and National Masonry says crusher dust is not recommended. Suppliers note it holds moisture and can cause white efflorescence staining. The industry association accepts crushed fines only when they are washed and meet its grading limits, so check with the paver maker before using crusher dust.

How deep do I dig for pavers?

Paver thickness plus bedding sand plus the compacted base. For 40 mm pavers on 30 mm of sand and 75 mm of road base, dig 145 mm below the finished level. A driveway with 60 mm pavers and a 150 mm base needs about 240 mm.

Sources and method

  1. Austral Masonry, Paver installation guide – base, bedding, joint widths.
  2. National Masonry, How to lay concrete pavers – road base depths, bedding sand, crusher dust.
  3. Adbri Masonry, Paver laying guide – pavers per m², 2 % allowance.
  4. Australian Paving Centre, DIY paving guide and paving area calculator – 75 / 150 mm bases, 5 % allowance.
  5. Firth, Paving installation guide (2026), and Dricon, PaveSand data sheet – NZ base depths and jointing sand coverage.
  6. Urban Paving, Installation guide for concrete pavers – base depths by soil strength from NZS 3116:2002.
  7. Concrete Masonry Association of Australia, PA02 Design of residential accessways and roads – paver thickness for vehicles, bedding thickness and grading.
  8. ABCB, NCC 2022 Housing Provisions Part 3.3 and Part 5.7 – surface fall, slab height and damp-proof course clearance; BRANZ, Build 570: Ground clearances – NZ.
  9. Densities: road base 2.2–2.4 t/m³ compacted and 1.9–2.1 t/m³ loose (Hunter Blue Metal, DGB20); washed river sand 1.5 t/m³. Example prices from ANL, September 2026.

Written by DueRiva · Last reviewed 23 September 2026 · Report an error